Mountlake Terrace Station Area

What’s happening in Mountlake Terrace in 2019?

TimeframeThe WorkGeneral LocationWhat to Expect
As early as late January CenturyLink utility relocation work around Mountlake Terrace Transit Center at 60th Ave W Mountlake Terrace Transit Center Trucking and some traffic impacts where utilities are in the public ROW
As early as January – May (5-month duration) Snohomish County Public Utility District (Sno PUD) duct bank and cable relocation at 212th St SE, 52nd Ave W and Interurban 212th St SW , 52nd Ave W and Interurban Trucking and some traffic impacts where utilities are in the public ROW
As early as January – February (2-month duration) Sno PUD underground utility relocation at SR 104/NE 205th St SR 104/NE 205th St Trucking and some traffic impacts where utilities are in the public ROW
As early as April – June 2019 Demolition of structures Along entire guideway alignment Trucking and noise from the demolition of structures
As early as May – August 2019 Clearing and tree removal for guideway installation Along entire guideway alignment Trucking and noise from tree removal and clearing equipment
November 2019 – November 2021 Excavation, retaining wall, and track bed construction for at-grade/retained cut guideway North of MLT Station, 228th St SW – 222nd St SW, 60th Ave W – 212th St SW Heavy equipment and trucking, noise from construction activities
December 2019 – July 2022 Drilled shaft, column, girder placement, and deck construction of elevated guideway at 175th St NE 205th St – MLT Station, 220th St SW, 212th St SW Heavy equipment and trucking, noise from construction activities
December 2019 – July 2022 Mountlake Terrace Station Mountlake Terrace Transit Center Heavy equipment and trucking, noise from construction activities, offsite parking for phased construction
As early as June 2019 Portion of Mountlake Terrace Transit Center Park & Ride surface lot closing Mountlake Terrace Transit Center Park & Ride surface lot Temporary parking will be located at what is currently the Roger’s Market site located at 232nd St SW and 57th Ave W. Additional information to be shared in spring 2019. More information and map on Parking relocation page