Shoreline North/185th Station Area

What’s happening in north Shoreline in 2019?

TimeframeThe WorkGeneral LocationWhat to Expect
As early as March – June (3-month duration) CenturyLink and Seattle City Light overhead utility relocation NE 165th, NE 167th, NE 170th, NE 180th, NE 185th, NE189th, and NE 200th streets Trucking and some traffic impacts where utilities are in the public ROW (right-of-way)
As early as April – June Removal of sound walls and demolition of structures Along east side of I-5 for guideway alignment Trucking and noise from the demolition of structures
As early as April – November (8-month duration) Power pole foundations and overhead power line relocation NE 180th, NE 185th and NE 200th streets Drill rigs and noise as foundations are constructed
As early as May – August Clearing and tree removal for guideway installation Along east side of I-5 for guideway alignment Trucking, noise and vibration from tree removal and clearing equipment
As early as July – October Stormwater and sewer relocation Along 5th Ave NE and guideway alignment Trucking and some traffic impacts where utilities are in the public ROW

Starting as early as December

CenturyLink and Comcast utility relocation at NE 185th St, 5th Ave NE and 8th Ave NE 5th Ave NE and 8th Ave NE Trucking and some traffic impacts where utilities are in the public ROW
Starting as early as December Seattle City Light duct bank and underground utilities Along the alignment Trucking and some traffic impacts where utilities are in the public ROW