Timeframe (subject to change)The WorkGeneral LocationWhat to Expect
As early as April – May (2-month duration) CenturyLink utility relocation NE 117th , NE 125th, NE 155th, and NE165th streets Trucking and some traffic impacts where utilities are in the public ROW (right-of-way)
As early as April – May (2-month duration) Utility relocations near I-5 and NE 125th St NE 125th St Trucking and some traffic impacts where utilities are in the public ROW
As early as April – June (3-month duration) Utility relocations at NE 155th St NE 155th St Trucking and some traffic impacts where utilities are in the public ROW
Starting as early as January – March (3-month duration) Overhead power line relocation Various locations along alignment Trucking and some traffic impacts where utilities are in the public ROW
As early as April – November (8-month duration) Power pole foundations and overhead power line relocation NE 123rd and NE145th streets Drill rigs and noise as foundations are constructed
As early as April – June Removal of sound walls and demolition of structures Various locations along alignment Trucking and noise from the demolition of structures
As early as May – August Clearing and tree removal for guideway installation Along east side of I-5 for guideway alignment Trucking, noise and vibration from tree removal and clearing equipment
October 2019 – October 2021 Drilled shaft, column, girder placement, and deck construction of elevated guideway Northgate Mall to NE 115th, NE 125th to NE 151st, NE 155th St Heavy equipment and trucking, noise from construction activities
October 2019 – June 2022 Excavation, retaining wall, and track bed construction for at-grade/retained cut guideway NE 115th to NE 125th, NE 151st to NE 165th St Heavy equipment and trucking, noise from construction activities